NameKyle Tanner
EmailEmail hidden; Javascript is required.
Partner Names
  • Myles Moore
Total Hours15
Descriptionrepairing trailer axle for dump trailer.
Notes

Originally spent the 5 hrs. fixing it after it bent on 3 separate occasions. including the first axle that was bent (not sure who used it the first 2 times) the 3rd time it bent on myself (not overloaded but at the weight limit of the trailer) noticed sever issues with the metal they used its very poor quality. the decision was made to test and research some new materials to use. we ended up deciding to use 4030 steel for strength and bend resistance. Cut away existing axel Myles machined down the rod to fit our new measurements and needs. I welded on plates reinstalled. fixed several other small issues noted with the trailer such as a loose bushing and a broken pin. Will check back after a few heavy uses and see if any new issues arrise.