Date of Trail Inspection/Ride08/02/2024
Your NameMyles Moore
Your EmailEmail hidden; Javascript is required.
Start Time07:30 AM
End Time03:30 PM
Total Hours8
COKL AREA: Trail and/or Staging Area Number
  • VRT North (Fenelon to Kinmount)
5-POINTS AREA: Trail and/or Staging Area Number
KORMA Single Track Trail(s) and Staging Area(s)
Total KMs Traveled on Trail65
Trail Hazards Still to Be Corrected
Identify any issues with club tools/machines that needs attention.
Trail Maintenance and/or Repairs CompletedApplied calcium in Burnt River, log chateau, and part of the vrt from Northline towards fenelon.
Trail Hazard Photos
Trail Hazard Locations
Partner Name(s) if not in the list above
Notes

We had some problems today with the valve on the water tank. It seemed the calcium glued it shut. We talked to lucas and he said we cold use one of his tanks so we changed the tank then was able to apply calcium. We only managed to do a small portion from northline towards Fenelon because of this equipment failure. That stretch from northline to garnet Graham still needs to be done. We flushed and cleaned the tank very well after this use so time will tell if that valve will work next time.