Date of Trail Inspection/Ride05/03/2025
Your NameSimon Martin
Your EmailEmail hidden; Javascript is required.
Start Time08:30 AM
End Time02:30 PM
Total Hours6.0
COKL AREA: Trail and/or Staging Area Number
  • VRT North (Fenelon to Kinmount)
  • Trail 10 (Beginner Trail)
  • Trail 11 (Beginner Trail)
  • Trail 17 (Beginner Trail)
  • Trail 31 (Boiler Trail)
  • Trail 70 (Intermediate Trail)
  • P2 - 93 Pinery Road Staging Area
  • P3 - Pinery Rd / 11 Conc Staging Area
  • P5 - Kinmount Train Station
5-POINTS AREA: Trail and/or Staging Area Number
KORMA Single Track Trail(s) and Staging Area(s)None
Total KMs Traveled on Trail44
Trail Hazards Still to Be Corrected
Identify any issues with club tools/machines that needs attention.
Trail Maintenance and/or Repairs CompletedCleared ice storm damage
Trail Hazard Photos
Trail Hazard Locations
Partner Name(s) if not in the list above
  • Dan Boyes
  • Penny Barriball
  • Shawn Suggest
Notes

Howard was with us and will be submitting a separate report for his hours as he stayed later than we did

Note that only a portion of trail 10 has been cleared by the city. We cleared to allow access only. Trail 70 and 71 were not finished and will require additional effort to finish them.

Boiler Trail 31 was completed by the city contractor up to trail 81. We did not venture onto trail 81 as the group consensus was that it was too extreme 🙂

A group of riders (3 ATV's & 1 SxS) came up behind us claiming that they did not know the trails were closed. They were turned around and sent home.